Change Input Value Across Projects was created by Paul Gilman
Please Log in or Create an account to join the conversation.
- LamprosSolar
Less
More
- Posts: 3
27 Jul 2014 07:24 #2416
by LamprosSolar
Replied by LamprosSolar on topic Change Input Value Across Projects
Hi Paul,
I created three cases using the same parameters except for financing. I used 0%, 50% and 100% debt fractions for the three scenarios. When I do a compare between cases, I end up with the same payback periods for all three. I would expect a shorter period for the case with no financing, longer for 100%. Can you explain this?
Thanks,
Tom Lampros
I created three cases using the same parameters except for financing. I used 0%, 50% and 100% debt fractions for the three scenarios. When I do a compare between cases, I end up with the same payback periods for all three. I would expect a shorter period for the case with no financing, longer for 100%. Can you explain this?
Thanks,
Tom Lampros
Please Log in or Create an account to join the conversation.
- Paul Gilman
- Topic Author
Less
More
- Posts: 5572
28 Jul 2014 11:52 #2417
by Paul Gilman
Replied by Paul Gilman on topic Change Input Value Across Projects
Dear Tom,
Please see the explanation of payback period and debt at the bottom of the page of the Payback Period topic in SAM's Help system:
SAM Help - Payback Period
Best regards,
Paul.
Please see the explanation of payback period and debt at the bottom of the page of the Payback Period topic in SAM's Help system:
SAM Help - Payback Period
Best regards,
Paul.
Please Log in or Create an account to join the conversation.
Moderators: Paul Gilman