10 Sep 2025 12:44 #14278 by inreco
Changeing Original Output was created by inreco
So, when one starts a project in SAM, it askes you what output your're seeking of your solar farm.  I selected 100MW.  By the time I finished with all the other inputs, the financials come up with 330MW and a prices tag that I don't want.  So why does it do that and how does one bring it back down to 100mw and a reasonable price tag??  Thanks!

Please Log in or Create an account to join the conversation.

  • Paul Gilman
More
12 Sep 2025 15:45 #14286 by Paul Gilman
Replied by Paul Gilman on topic Changeing Original Output
Hello,

It is up to you to size the system on the System Design page and set the project costs on the Installation Costs and Operating Costs input pages.

Please attach a copy of your .sam file if you would like me to help troubleshoot.

Best regards,
Paul.

Please Log in or Create an account to join the conversation.

  • inreco
  • Topic Author
More
13 Sep 2025 14:30 #14288 by inreco
Replied by inreco on topic Changeing Original Output
So even though I stipulated, at the start 100mw and then after all the other inputs, it calculates the actual output?
So, the way to reduce that is to reduce the number of modules/string? And that also is a way to reduce total construction cost?

Please Log in or Create an account to join the conversation.

  • Paul Gilman
More
16 Sep 2025 09:33 #14292 by Paul Gilman
Replied by Paul Gilman on topic Changeing Original Output
Hello,

If you design a PV system with a nameplate capacity of 100 MW, when you run a simulation, SAM calculates the system's output in each hour based on the inputs you provide and the data in the weather file. On clear sunny days, the output should be close to 100 MW.

The inputs for project installation costs are on the Installation costs page. For the the Single Owner financial model, there is a construction financing cost (cost of interest accrued for construction loans during the construction period) calcuator on the Financial Parameters page.

Best regards,
Paul.

Please Log in or Create an account to join the conversation.

  • inreco
  • Topic Author
More
16 Sep 2025 14:16 #14294 by inreco
Replied by inreco on topic Changeing Original Output
 

File Attachment:

File Name: Zinshine 7...00mw.sam
File Size:109 KB
as far as financials, i mentioned this before. VC's don't charge interest just a flat fee and a ten-year payback period and it doesn't' seem that your system can accommodate this scenario. maybe it can but i can't figure it out. So, put the 20 mil in "Cost of Acquiring Financing" and the total Install cost that it comes up with $94 mil isn't visible in the cash flow financial and neither is the Net Capital Cost of $118 mil

Please Log in or Create an account to join the conversation.

  • Paul Gilman
More
16 Sep 2025 15:19 #14295 by Paul Gilman
Replied by Paul Gilman on topic Changeing Original Output
Hello,

Those costs should be shown on the Cash Flow tab of the Results page under "Investing Activities:"

 

Best regards,
Paul.