27 Aug 2025 14:24 #14258
by inreco
Replied by inreco on topic Tips For System Sizing
So I replaced the .lk file and ran the sizing macro until I got rid of the errors "Increase/decrease the number of inverters or modules in string.... But now my NPV is negative.
Did my pdf upload?
Did my pdf upload?
Please Log in or Create an account to join the conversation.
- Paul Gilman
Less
More
- Posts: 5626
28 Aug 2025 14:50 #14261
by Paul Gilman
Replied by Paul Gilman on topic Tips For System Sizing
Hello,
For a behind-the-meter project, the negative NPV is an indication that the project costs may be higher than the electricity bill savings over the project life.
See the "Net Present Value" topic in Help for a list of possible reasons the NPV is negative and ways to make it more positive: samrepo.nrelcloud.org/help/mtf_npv.html .
Best regards,
Paul.
For a behind-the-meter project, the negative NPV is an indication that the project costs may be higher than the electricity bill savings over the project life.
See the "Net Present Value" topic in Help for a list of possible reasons the NPV is negative and ways to make it more positive: samrepo.nrelcloud.org/help/mtf_npv.html .
Best regards,
Paul.