        Payback time for CSP Power Tower was created by anthony_vanoli            
    
        Hi !
I'm studying the possibility of installing a CSP power tower in France so I'd like to know how to walwulate the payback time for such a technology.
I've already sized my system, I found some Excel files on the site but none of them is useful o me to calculate a payback time (because of a problem of size of tables in the files). If anybody can help, it would be nice.
Thanks a lot.
    I'm studying the possibility of installing a CSP power tower in France so I'd like to know how to walwulate the payback time for such a technology.
I've already sized my system, I found some Excel files on the site but none of them is useful o me to calculate a payback time (because of a problem of size of tables in the files). If anybody can help, it would be nice.
Thanks a lot.
Please Log in or Create an account to join the conversation.
- Paul Gilman
        Less
        More
        
            
    
        - Posts: 5665
            
        
                03 Apr 2013 06:02                #1500
        by Paul Gilman
    
    
            
            
            
            
            
                                
    
                                                
    
        Replied by Paul Gilman on topic Payback time for CSP Power Tower            
    
        Hello,
SAM's power tower models in SAM can only be used with one of the PPA models (Utility IPP, Single Owner, etc.). For those models, SAM calculates a PPA price or project IRR, NPV, and other metrics appropriate for large, power generation project. SAM only calculates the payback period for the residential and commercial financial models, which are not available for the power tower models.
If you want to calculate the payback period, you can export the year zero investment amount and energy value row from the project cash flow, and calculate it outside of SAM.
Best regards,
Paul.
    SAM's power tower models in SAM can only be used with one of the PPA models (Utility IPP, Single Owner, etc.). For those models, SAM calculates a PPA price or project IRR, NPV, and other metrics appropriate for large, power generation project. SAM only calculates the payback period for the residential and commercial financial models, which are not available for the power tower models.
If you want to calculate the payback period, you can export the year zero investment amount and energy value row from the project cash flow, and calculate it outside of SAM.
Best regards,
Paul.