19 Feb 2013 11:27 #1335
by asaraf
Is LADWP performance based incentive being approximated? was created by asaraf
When I lookup incentives in Los Angeles, CA, I get an option to choose an LADWP performance based incentive (PBI) at a fixed value of $0.12/kWh.
However, when I look up the details of the incentive from DSIRE, it is more complicated than that, as the incentive varies with time of use ( www.dsireusa.org/solar/incentives/incentive.cfm?Incentive_Code=CA258F&re=1&ee=1 ).
Is SAM averaging the time of use values, or is it a different incentive, or something else? If it is averaging the incentive to a single fixed number, does anyone know how exactly it is doing so?
However, when I look up the details of the incentive from DSIRE, it is more complicated than that, as the incentive varies with time of use ( www.dsireusa.org/solar/incentives/incentive.cfm?Incentive_Code=CA258F&re=1&ee=1 ).
Is SAM averaging the time of use values, or is it a different incentive, or something else? If it is averaging the incentive to a single fixed number, does anyone know how exactly it is doing so?
Please Log in or Create an account to join the conversation.
- pgilman
Less
More
- Posts: 5423
25 Feb 2013 12:59 #1336
by pgilman
Replied by pgilman on topic Is LADWP performance based incentive being approximated?
Hello,
The value that SAM is downloading from the DSIRE database does seem inconsistent with the description of the LADWP incentive. SAM does not manipulate the data from the database, it simply downloads values as they are stored in the database. I will have our developers look into this particular issue to see what the problem might be.
That said, rather than relying on the download feature, I would specify the incentive by hand using the SAM inputs to be sure you model the incentive as you intend to. Depending on the project you want to model, you may want to model the feed-in tariff in SAM as a utility rate instead of a performance-based incentive (PBI). You can specify time-dependent rates on the Utility Rates page, but it is not possible to specify a time-dependent PBI (except for one whose value varies from year to year).
Best regards,
Paul.
The value that SAM is downloading from the DSIRE database does seem inconsistent with the description of the LADWP incentive. SAM does not manipulate the data from the database, it simply downloads values as they are stored in the database. I will have our developers look into this particular issue to see what the problem might be.
That said, rather than relying on the download feature, I would specify the incentive by hand using the SAM inputs to be sure you model the incentive as you intend to. Depending on the project you want to model, you may want to model the feed-in tariff in SAM as a utility rate instead of a performance-based incentive (PBI). You can specify time-dependent rates on the Utility Rates page, but it is not possible to specify a time-dependent PBI (except for one whose value varies from year to year).
Best regards,
Paul.
Please Log in or Create an account to join the conversation.
- asaraf
- Topic Author
Less
More
- Posts: 3
10 Apr 2013 15:31 #1337
by asaraf
Replied by asaraf on topic Is LADWP performance based incentive being approximated?
Thank you, Paul. Please do reply back if your developers find anything.