BESS Simulation

  • Emilio Corral
  • Topic Author
More
25 Nov 2022 22:13 #11721 by Emilio Corral
BESS Simulation was created by Emilio Corral
Hi Paul,

I hope your week is going well so far!

I'm doing a PPA simulation for a BESS.
Here in Ontario, customers reduce their peak demand during the IESO coincident peaks in order to reduce the global adjustment costs, and that reduces their bills. This is done by dispatching the BESS during peak periods.

How can I include an annual incentive based on MW installed at the facility?

I found the way if we had PV+BESS under capacity payments, but the Revenue tab is not available if I select only BESS.

I look forward to hearing from you.

Best Regards,

Rafael

Please Log in or Create an account to join the conversation.

  • Paul Gilman
More
28 Nov 2022 18:23 #11727 by Paul Gilman
Replied by Paul Gilman on topic BESS Simulation
Hi Rafael,

The Standalone Battery / Single Owner configuration has input pages for Revenue and Incentives where you can specify dollar values in dollars per unit of installed capacity.

On the Incentives page, the Capacity Based Incentive (CBI) is a one-time direct cash payment calculated from the system nameplate capacity in Watts. On the Revenue page, the capacity  payment is annual revenue calculated from the system nameplate capacity in megawatts.

Best regards,
Paul.

Please Log in or Create an account to join the conversation.

  • Emilio Corral
  • Topic Author
More
28 Nov 2022 19:00 - 28 Nov 2022 19:10 #11733 by Emilio Corral
Replied by Emilio Corral on topic BESS Simulation
Hi Paul,

I changed the model to Single Owner, and was able to find the Revenue tab, along with the Capacity annual payment.
However, the model is not creating the report although the simulation does run correctly.
The following message appears,
Last edit: 28 Nov 2022 19:10 by Paul Gilman.

Please Log in or Create an account to join the conversation.

  • Paul Gilman
More
28 Nov 2022 19:12 #11735 by Paul Gilman
Replied by Paul Gilman on topic BESS Simulation
Hi Emilio,

A PDF report for the merchant plant financial model is not available. You can create your own report with the data you need for your project using the techniques described in the "Export Data and Graphs" topic of Help:

samrepo.nrelcloud.org/help/export_data.htm

Best regards,
Paul.