Can Sam Model part of the year operation?
- Harry_Ha
- Topic Author
Less
More
11 Oct 2020 10:51 #8852
by Harry_Ha
Can Sam Model part of the year operation? was created by Harry_Ha
Hi, there
I am modeling a IPH process at Northern Alberta, Canada location, where there are four months the CSP will not operational. So can I just let SAM model the IPH process from March to October only for financial model. The CSP will be shutdown and protected during the no operational period.
Thanks,
Harry
I am modeling a IPH process at Northern Alberta, Canada location, where there are four months the CSP will not operational. So can I just let SAM model the IPH process from March to October only for financial model. The CSP will be shutdown and protected during the no operational period.
Thanks,
Harry
Please Log in or Create an account to join the conversation.
- pgilman
Less
More
- Posts: 5423
12 Oct 2020 09:44 #8856
by pgilman
Replied by pgilman on topic Can Sam Model part of the year operation?
Hi Harry,
You can use the "system availability" losses on the System Control page to model this scenario: Set the loss to 100% for all times when the system will not deliver heat.
Best regards,
Paul.
You can use the "system availability" losses on the System Control page to model this scenario: Set the loss to 100% for all times when the system will not deliver heat.
Best regards,
Paul.