Get size and dispatch doubt

  • fdml
  • Topic Author
More
24 Sep 2020 13:26 #8775 by fdml
Get size and dispatch doubt was created by fdml
Hi, I created a PVWatts Battery Commercial case, when I change the electricity rate I got this error: Could not evaluate callback function:call_reopt->on_change
[10]: error in call to 'reopt_size_battery()': ElectricityRates_format_as_URDBv7 error. Unit type in ur_ec_tou_mat not allowed.[8]: eval error in statement list.

I used this rate Bagley Public Utilities Comm: Commercial Electric Three Phase.

Why I'm getting this error?

Please Log in or Create an account to join the conversation.

  • pgilman
More
25 Sep 2020 23:51 #8784 by pgilman
Replied by pgilman on topic Get size and dispatch doubt
Hi Diego,

SAM and REopt appear to be working with different versions of the utility rate database (URDB). We are working to resolve this issue: github.com/NREL/SAM/issues/361.

Best regards,
Paul.