Hi,
I wonder where I can get information on detailed offshore balance of system cost model inputs.
For example, there are inputs for cables under Assembly & Installation as listed below:
array_cable_loadout_for_installation 14
array_cable_pull_in_to_interfaces 5.5
cable_burial_rate 125
cable_landfall_dive_team_day_rate 3200
cable_landfall_winch_day_rate 1000
cable_pull_in_to_offshore_substation 48
cable_pull_in_to_onshore_infrastructure 96
cable_route_survey_cost 240
cable_surface_lay_rate 375
cable_termination_and_testing 5.5
export_cable_loadout_for_installation 24
what is the unit? which inputs apply for array cable and export cable? these kind of questions can be answered intuitively, but I would like to know whether written description is available as there are many more inputs.
I cannot find those from "NREL Offshore Balance-ofSystem Model" in this link
www.nrel.gov/docs/fy17osti/66874.pdf